Sunshine Coast rail upgrade lays groundwork for new modern trains

Do you have a news tip? Click here to send to our news team.

Cyclone spirals closer, campers urged to leave sites

Powerful waves could cause floods and coastal erosion as a tropical cyclone narrows on Queensland's coast, but the category three system is unlikely to More

Vision for second solar farm on Coast

An interstate property firm has designs on establishing a solar project alongside the existing Sunshine Coast Solar Farm. VIMG owns nearly 100 hectares of former More

Hinterland B&B up for national recognition

A Sunshine Coast hinterland bed and breakfast is in the running for a national tourism award next month. The Country House at Hunchy is a More

Flexible learning hub to receive $520K boost

An education centre that helps secondary school students stay engaged will get a half-a-million-dollar funding boost. The Virtues Improving Relational Behaviours (VIRB) Education Hub at More

Boater’s dream: rare low-set waterfront home on market

A waterfront home is on the market after 24 years under its current owners. The property at 21 Myoora Court, Minyama, has been updated over More

Photo of the day: soothing sundown

Helen Browne was on the scene to capture the colours as the sun set beyond the Mooloolah River. If you have a photo of the More

New signalling technology is being installed on the Sunshine Coast rail line which will lay the groundwork for introducing the “next generation” of modern trains.

The $45 million signalling project is described as an “autopilot” system which can “take over” control of the train from the driver and improve safety.

It comes as work is expected to start later this year on the Sunshine Coast Rail Duplication, duplicating 20km between Beerburrum and Landsborough and upgrades to Nambour.

The first phase of the $550million duplication project will include a realignment of sections of Steve Irwin Way and the installation of Park and Ride facilities at Nambour and Landsborough.

Work on the signalling project started at Gympie and is now focussed on the Nambour area as the project continues towards Caboolture.

Construction leader Ben Cue, from Rail Control Systems which is leading the project, said the signalling technology was like an autopilot for trains which could read and react to problems along the line.

About 60 workers are involved in rolling out the European Train Control System (ETCS) level one technology.

Transport and Main Roads Minister Mark Bailey said 130 signal equipment cubicles would be upgraded and 43 new equipment cubicles installed over 120 kilometres of track.

Mr Bailey said the project was not only supporting local jobs, it was also gearing up the North Coast rail line for improved services between the Sunshine Coast and Brisbane ahead of Cross River Rail opening in 2025.

“Installing ETCS technology on the line means we’ll be able to put the newer NGR (Next Generation Rollingstock) class trains into services up to Gympie,” Mr Bailey said.

“Integrating ETCS and Automatic Train Protection (ATP) systems along the line is also an important step in preparing for track duplication between Beerburrum and Landsborough.

“Once installation has been completed along the track and onboard trains, the new infrastructure will provide an engineering control to ensure trains stop before the red signal.”

The Beerburrum to Nambour Rail Upgrade is due to start towards the end of 2021.

Member for Nicklin Robert Skelton said the upgrades would enable more modern trains “which will be welcomed by the thousands of people who commute to work every day”.

“Crews started work near Gympie last September and have been progressively making their way south,” he said.

“This project will continue to support a significant number of jobs through to the middle of next year until the crews finish their work just south of Caboolture.

“Works are about to ramp up on the Sunshine Coast Rail Duplication project, so I’m pleased to see the work is being done to equip the rail line with signalling technology that is increasingly being adopted on major rail systems across the world.”

As part of the Cross River Rail project, a new signalling system is also being installed across sections of the inner-city network, using ETCS level two technology.

The works will be rolled out in several stages starting with the Shorncliffe line, where work has already started.