What's holding up construction of new homes as builders battle tight handover deadlines

Do you have a news tip? Click here to send to our news team.

Historic town’s new-look streetscape unveiled

A Sunshine Coast town's main street has a new look. Landsborough's Cribb Street has been revitalised by a streetscape project that included introducing a range More

‘Immaculate’ home steps from the beach an ‘entertainer’s dream’

A modern home less than 100 steps from the beach in a sought-after neighbourhood is poised for auction. The corner home boasts luxury and convenience More

Feedback split but council gives nod to luxury hotel relaxations

The Sunshine Coast Council has approved a temporary local planning instrument allowing height and carparking relaxations for luxury hotel developments for the next two More

Rebuild forces cancellation of popular Christmas festival

An annual Christmas event that draws tens of thousands of people to a Coast church will not go ahead this year, in what is More

‘I just wanted to do something different, so I built a chateau’

A man’s home is his castle – or a chateau, in the case of the man behind one of the country’s best-known building brands. G.J More.

Car found after grandmother’s mysterious death

The bizarre disappearance and death of a Queensland grandmother who was last seen on the Sunshine Coast has taken another turn. Police have located a More

House builders, who are already under pressure to deliver on the raft of new homes under contract due to the first home buyers’ grant schemes, now have their backs against the wall for another complex reason.

Regional General Manager QLD for CSR Construction Systems, Ross Norman, says the schemes provided a great boost to the residential building industry, but several builders who eagerly signed contracts have found they can’t meet the handover deadlines.

A shortage in timber is causing a lot of the problems. The bushfires impacted on supply and so too has the cessation of Australian timber supplies from Canada due to the high tax tariff.

“Framing companies have pre-bought and wrapped up their allocations,” Mr Norman explains.

“They traditionally were able to get out 25 or 30 frames a month or a week, but they have had to forward order three to six months and they now are allocating probably one-third of those framing allocations because of such a shortage in timber.”

Help keep independent and fair Sunshine Coast news coming by subscribing to our free daily news feed. All it requires is your name and email. See SUBSCRIBE at the top of this article 

Steel prices have also risen by between 12 and 37 per cent.

With fixed price contracts in place and build costs now up by between 20 and 40 per cent, some builders are finding they have to go back to the consumer with revised options as their pricing does not stack up.

“Consumers are getting concerned and some are choosing to cancel their contract,” Mr Norman says.

“A lot of builders are happy to give back deposits because they can’t meet their obligations.”

Ross Norman from CSR Construction Systems

These builders are looking for alternative framing solutions and façade options such as autoclaved aerated concrete (AAC), which CSR markets as Hebel.

“Hebel is getting substituted in for a lot of façade work over bricks as there is a shortage of bricklayers and their prices are going up,” Mr Norman says.

The builders can self-perform the use of AAC which can eliminate the need for a façade specialist. “I think that is extremely smart,” he adds.

Mr Norman believes that AAC is going to be an ongoing choice by builders.

“I really think they are going to have to otherwise we are going to see so many really good builders not around and that is a shame,” he says. “The bigger ones will get bigger, and the smaller ones could fade away.

“I think that is a big blight on the industry if we lose good builders and don’t support them.”